Vietnam has broken ground on its first international subsea fibre-optic cable initiated and led by a Vietnamese company — a shift from mainly contributing capital and buying capacity to planning the route and designing the system for its own connectivity infrastructure.
The VTS cable: the key figures
- On 26 November, in Ho Tram commune, Ho Chi Minh City, the VTS consortium co-led by Viettel and Singtel officially broke ground on a subsea fibre-optic cable linking Vietnam, Thailand and Singapore. It is the first international subsea fibre-optic cable initiated and led by a Vietnamese company.
- The full route is about 2,500 km long, with a design capacity of 600 Tbps, and is scheduled for completion in the fourth quarter of 2030. The Vietnam–Singapore leg alone is about 1,200 km and carries 240 Tbps — roughly 2.5 times the combined capacity of the international cables Vietnam currently operates.
- The main trunk will be buried about 3 m beneath the seabed to reduce the risk of damage from fishing and ships dropping anchor.
Why this is more than just another cable
- Until now, Vietnamese companies have mostly taken part by contributing capital and using available capacity on cables built by international consortia. With VTS, Viettel initiated the project, signed a memorandum of understanding with Singtel in April 2024, and directly leads route planning and design — the key stages that determine landing points, configuration and the performance of the whole system.
- Partners in the project include AIS (Thailand), VNPT, FPT Telecom and Viettel IDC; the two construction contractors are NEC (Japan) and ASEAN Cableship (Singapore).
- Deputy Minister of Science and Technology Pham Duc Long framed the project as a shift "from mainly using international connectivity to helping build it". Viettel aims to invest in 10 international cables and lead at least 2 by 2030. The project is tied to Resolution 57 on breakthroughs in science, technology, innovation and digital transformation, and to Vietnam's strategy for developing its international fibre-optic cable system to 2030.
For a country whose cloud-computing and artificial-intelligence ambitions run on bandwidth rented from foreign-led cable consortia, owning the route is both a strategic asset and a commercial one. The test, of course, is execution: the fourth-quarter 2030 completion date is still four years away, and in that time costs, technology and geopolitics can all change.
Sources: Stockbiz; TechNode Global; VCCI; CafeBiz; HTV.
Nguon Tin Viet Editorial Board
#SubseaCable #Vietnam #Viettel #DigitalInfrastructure #SouthEastAsia


01:19
Nguon Tin Viet

Posted in:
0 comments:
Post a Comment